Works of construction of pier n. IV, services dock and sedimentation basin for the dredged material as part of the public contract for the concession of design, construction and management of the new logistics platform in the Port of Taranto.
Description of the works:
Taranto Port Authority stipulated a concession with the Company Taranto Logistica S.p.A. for the design, construction and subsequent management of the Logistics Platform of the Port of Taranto under Project Financing.
Taranto Logistica S.p.A. assigned, with the consent of the Grantor, the execution by any means of all the works to the General Contractor ACI S.c.p.A. The maritime works have then been assigned to Fincosit.
Maritime works are:
- Mine clearance of the working areas;
- Sedimentation basin for the dredged material. The water tightness of the perimeter of the basin is guaranteed by sheet piling (seaside) and flexible diaphragm (landside). In the sedimentation basin a quay for barges is foreseen;
- Excavation and remediation of the contaminated sediments and subsequent dredging of the areas in front of pier IV (to –12.00 m m.s.l.) and in front of the services dock (to –7.00 m m.s.l.). Excavation of the trench for the foundation of the caissons of pier IV (to –14.00 m m.s.l.);
- Expansion of the existing pier IV by constructing a new quay eastside, a head quay and a landside quay. All the quays are made of reinforced concrete precast cellular caissons founded on an excavation filled by rubble 5÷50 Kg at el.-12.70m m.s.l. The new total length is 600 m, the existing pier is expanded from 80 to 200 m.
- Construction of the first part of the mooring quay eastward of the services dock using reinforced concrete precast cellular caissons founded at –7.70 m m.s.l. The total length of the quay is 150m;
- Construction of a new jetty on bored piles (206 m)
Works of construction of pier n. IV, services dock and sedimentation basin for the dredged material as part of the public contract for the concession of design, construction and management of the new logistics platform in the Port of Taranto.
Description of the works:
Taranto Port Authority stipulated a concession with the Company Taranto Logistica S.p.A. for the design, construction and subsequent management of the Logistics Platform of the Port of Taranto under Project Financing.
Taranto Logistica S.p.A. assigned, with the consent of the Grantor, the execution by any means of all the works to the General Contractor ACI S.c.p.A. The maritime works have then been assigned to Fincosit.
Maritime works are:
- Mine clearance of the working areas;
- Sedimentation basin for the dredged material. The water tightness of the perimeter of the basin is guaranteed by sheet piling (seaside) and flexible diaphragm (landside). In the sedimentation basin a quay for barges is foreseen;
- Excavation and remediation of the contaminated sediments and subsequent dredging of the areas in front of pier IV (to –12.00 m m.s.l.) and in front of the services dock (to –7.00 m m.s.l.). Excavation of the trench for the foundation of the caissons of pier IV (to –14.00 m m.s.l.);
- Expansion of the existing pier IV by constructing a new quay eastside, a head quay and a landside quay. All the quays are made of reinforced concrete precast cellular caissons founded on an excavation filled by rubble 5÷50 Kg at el.-12.70m m.s.l. The new total length is 600 m, the existing pier is expanded from 80 to 200 m.
- Construction of the first part of the mooring quay eastward of the services dock using reinforced concrete precast cellular caissons founded at –7.70 m m.s.l. The total length of the quay is 150m;
- Construction of a new jetty on bored piles (206 m)